Winter Park · Phase 1

Park Avenue
Refresh

Garfield to Swoope
Civil detail
New pipeExisting pipe
Utility plans ↗
Drawing sources

Current construction reach: Garfield Avenue to Swoope Avenue.

Design drawings show plan locations. Field changes may differ.

Phase 1 reference drawings ↗
Canton paving & curb · C4.2 ↗
Canton ramp & bollard details · C6.1 ↗
East Cole raised planter · L2.02 ↗
Original conduit plan · November 2025 ↗
Swoope utility phase break · January 2026 ↗
Signal conduits · May 2026 ↗

Civil: revised engineering CAD and final Canton details.
Survey: 241001 Survey Features to Poly.
Landscape: final hardscape and August field revisions.
Lighting: tagged landscape plan locations.

Preliminary quantities

Plan quantities unless marked estimated or installed.

SF = square feet · LF = linear feet

Pending quantities
Takeoff notes

Decorative bollards: 30 Canton, 8 Cole, 2 Garfield and 2 approved east Cole additions. Pot bollards are counted separately. Installed bollard totals remain unconfirmed.

Light poles: City count of 20; 19 plan locations mapped. Pots follow the August 26 direction. Hanging baskets are field-confirmed.

Landscaped area includes tree wells and raised-bed interiors. Raised-bed area is part of that total. Wall lengths follow centerlines.

Stormwater pipe: 169 LF from the four Civil plan callouts; existing pipes excluded.

Conduit: Hector’s January 22 estimate totals 7,550 LF across utilities. The utility-by-utility split and installed footage remain unconfirmed.

View report ↗CSV ↓