Project quantities
Garfield Avenue to Swoope Avenue · October 8, 2026
| Item | Quantity | Basis |
|---|---|---|
| Light poles | 20 each | City count 19 tagged plan locations mapped; one position still to reconcile |
| Hanging baskets | 40 each | Installed Installed count confirmed by Alex Stringfellow · October 7, 2026 |
| Pots | 35 each | Revised scope · August 26 12 medium · 12 large · 11 small |
| Trash / recycling | 10 each | Plan count 7 trash cans · 3 recycling bins |
| Decorative bollards | 42 each | Plan + approved additions 30 Canton · 8 Cole · 2 Garfield · 2 approved east Cole additions. Excludes pot bollards and the rejected nine-bollard Garfield run. Installed total remains unconfirmed. |
| Pot bollards | 12 each | August field direction One in each mapped Pot 1; installed total remains unconfirmed. Supersedes the May in-pot allocation. |
| Proposed trees | 8 each | Plan count Final tree-canopy sheets L-3.01/L-3.02: four live oaks and four crape myrtles; existing trees excluded |
| Raised planters | 7 each | Plan count Includes the east Cole planter |
| Raised planter walls | 391 LF | Measured plan length Wall perimeter at centerline, including the east Cole planter |
| Planter planting area | 1,150 SF | Measured plan area Interior planting area; masonry walls excluded |
| Landscaped areas | 3,469 SF | Measured plan area Tree wells and planting-bed interiors; masonry, pots and tree canopies excluded |
| Phase 1 length | 887 LF | Measured plan length 0.168 mile · Garfield to Swoope, street centerlines |
| New stormwater pipe | 169 LF | Civil plan callouts C5.2/C5.3: 38 LF of 18-inch RCP and 30 + 36 + 65 LF of 15-inch RCP. Four new runs only; existing pipes and excluded north Cole extension omitted. Mapped centerlines total 166.83 LF; printed plan callouts total 169 LF. Not an as-built measurement. |
| 2-inch conduit | 6,300 LF | Estimated · January 22, 2026 Hector scope-reduction estimate for Garfield to Swoope, including irrigation. Combined systems; allocation by utility and installed footage remain unverified. Individual conduit length, not bore length. |
| 4-inch conduit | 1,250 LF | Estimated · January 22, 2026 Hector scope-reduction estimate for Garfield to Swoope, including irrigation. Combined systems; allocation by utility and installed footage remain unverified. Individual conduit length, not bore length. |
| Irrigation conduit | Pending | Awaiting utility breakdown Included in the combined conduit estimate; no separate verified footage. Water-pipe lengths are not conduit lengths |
| Electrical conduit · Kishor | Pending | Awaiting utility breakdown Included in the combined conduit estimate; no separate verified footage. Wire-pull footage is not conduit footage |
| Electrical conduit · WPE | Pending | Awaiting utility breakdown Included in the combined conduit estimate; no separate verified footage |
| Fiber conduit | Pending | Awaiting utility breakdown Included in the combined conduit estimate; no separate verified footage. Cable-pull completion and conduit length are separate |
| Project workforce | Pending | Awaiting contractor count Unique workers across all subcontractors |
The measured reach is 0.168 mile, or 0.2 mile rounded to one decimal. Baskets: installed count confirmed on site by Alex Stringfellow. Pots: August 26 revised scope. Bollards: final permit locations, approved Cole additions and August Pot 1 direction; installed total remains to be confirmed. Landscaped area: measured, non-overlapping tree-well and planting-bed footprints from CAD and final permit drawings; excludes pots, canopy symbols and northern sod removed from scope.
Conduit: the January 22 reduced-scope estimate provides 6,300 LF of 2-inch conduit and 1,250 LF of 4-inch conduit, or 7,550 LF combined. These are estimated individual-conduit lengths, not bore-path or installed lengths. The 2,500 LF of #6 conductor in the same source is wire and is excluded. The split by utility and contractor remains unverified. New stormwater pipe: 169 LF from Civil sheets C5.2/C5.3; existing pipes and the excluded north Cole extension are omitted. Workforce requires a count of unique workers across all subcontractors.
Reference drawings · Design locations may differ from field placement.
Conduit: the January 22 reduced-scope estimate provides 6,300 LF of 2-inch conduit and 1,250 LF of 4-inch conduit, or 7,550 LF combined. These are estimated individual-conduit lengths, not bore-path or installed lengths. The 2,500 LF of #6 conductor in the same source is wire and is excluded. The split by utility and contractor remains unverified. New stormwater pipe: 169 LF from Civil sheets C5.2/C5.3; existing pipes and the excluded north Cole extension are omitted. Workforce requires a count of unique workers across all subcontractors.