StringfellowPark Avenue · Phase 1

Project quantities

Garfield Avenue to Swoope Avenue · October 8, 2026

ItemQuantityBasis
Light poles20 eachCity count
19 tagged plan locations mapped; one position still to reconcile
Hanging baskets40 eachInstalled
Installed count confirmed by Alex Stringfellow · October 7, 2026
Pots35 eachRevised scope · August 26
12 medium · 12 large · 11 small
Trash / recycling10 eachPlan count
7 trash cans · 3 recycling bins
Decorative bollards42 eachPlan + approved additions
30 Canton · 8 Cole · 2 Garfield · 2 approved east Cole additions. Excludes pot bollards and the rejected nine-bollard Garfield run. Installed total remains unconfirmed.
Pot bollards12 eachAugust field direction
One in each mapped Pot 1; installed total remains unconfirmed. Supersedes the May in-pot allocation.
Proposed trees8 eachPlan count
Final tree-canopy sheets L-3.01/L-3.02: four live oaks and four crape myrtles; existing trees excluded
Raised planters7 eachPlan count
Includes the east Cole planter
Raised planter walls391 LFMeasured plan length
Wall perimeter at centerline, including the east Cole planter
Planter planting area1,150 SFMeasured plan area
Interior planting area; masonry walls excluded
Landscaped areas3,469 SFMeasured plan area
Tree wells and planting-bed interiors; masonry, pots and tree canopies excluded
Phase 1 length887 LFMeasured plan length
0.168 mile · Garfield to Swoope, street centerlines
New stormwater pipe169 LFCivil plan callouts
C5.2/C5.3: 38 LF of 18-inch RCP and 30 + 36 + 65 LF of 15-inch RCP. Four new runs only; existing pipes and excluded north Cole extension omitted. Mapped centerlines total 166.83 LF; printed plan callouts total 169 LF. Not an as-built measurement.
2-inch conduit6,300 LFEstimated · January 22, 2026
Hector scope-reduction estimate for Garfield to Swoope, including irrigation. Combined systems; allocation by utility and installed footage remain unverified. Individual conduit length, not bore length.
4-inch conduit1,250 LFEstimated · January 22, 2026
Hector scope-reduction estimate for Garfield to Swoope, including irrigation. Combined systems; allocation by utility and installed footage remain unverified. Individual conduit length, not bore length.
Irrigation conduitPendingAwaiting utility breakdown
Included in the combined conduit estimate; no separate verified footage. Water-pipe lengths are not conduit lengths
Electrical conduit · KishorPendingAwaiting utility breakdown
Included in the combined conduit estimate; no separate verified footage. Wire-pull footage is not conduit footage
Electrical conduit · WPEPendingAwaiting utility breakdown
Included in the combined conduit estimate; no separate verified footage
Fiber conduitPendingAwaiting utility breakdown
Included in the combined conduit estimate; no separate verified footage. Cable-pull completion and conduit length are separate
Project workforcePendingAwaiting contractor count
Unique workers across all subcontractors
The measured reach is 0.168 mile, or 0.2 mile rounded to one decimal. Baskets: installed count confirmed on site by Alex Stringfellow. Pots: August 26 revised scope. Bollards: final permit locations, approved Cole additions and August Pot 1 direction; installed total remains to be confirmed. Landscaped area: measured, non-overlapping tree-well and planting-bed footprints from CAD and final permit drawings; excludes pots, canopy symbols and northern sod removed from scope.

Conduit: the January 22 reduced-scope estimate provides 6,300 LF of 2-inch conduit and 1,250 LF of 4-inch conduit, or 7,550 LF combined. These are estimated individual-conduit lengths, not bore-path or installed lengths. The 2,500 LF of #6 conductor in the same source is wire and is excluded. The split by utility and contractor remains unverified. New stormwater pipe: 169 LF from Civil sheets C5.2/C5.3; existing pipes and the excluded north Cole extension are omitted. Workforce requires a count of unique workers across all subcontractors.

Reference drawings · Design locations may differ from field placement.